work Breakdown Structure as regard to Ohio department of Human Services “E-mail
Software upgrade 2004.
Need assignment help for this question?
If you need assistance with writing your essay, we are ready to help you!
OUR PROCESS
Order
Payment
Writing
Delivery
Why Choose Us: Cost-efficiency, Plagiarism free, Money Back Guarantee, On-time Delivery, Total Сonfidentiality, 24/7 Support, 100% originality
WBS
|
WBS
|
Begin
|
Duration/days
|
Complete
|
1.0
|
Evaluate
|
05
|
7
|
12-April
|
1.1
|
Number
|
06
|
6
|
12-April
|
1.2
|
End
|
07-April
|
5
|
12-April
|
1.2.1
|
Surveys
|
08-April
|
4
|
12-April
|
1.2.2
|
Analysis
|
09-April
|
3
|
12-April
|
1.2.3
|
Drawing
|
10-April
|
2
|
12-April
|
2.0
|
Evaluate
|
13-April
|
6
|
19-April
|
2.1
|
Network
|
20-April
|
5
|
25-April
|
2.2
|
Output
|
22-April
|
4
|
25-April
|
3.0
|
Conduct
|
23-April
|
13
|
6-May
|
3.1
|
Reach
|
24-April
|
12
|
6-May
|
3.2
|
Ensure
|
25-April
|
11
|
6-May
|
4.0
|
Upgrade
|
7-May
|
54
|
30-June
|
4.1
|
Coding
|
8-May
|
53
|
30-June
|
4.2
|
System
|
9-May
|
52
|
30-June
|
5.0
|
Develop
|
1-July
|
64
|
4-Sept
|
5.1
|
Training
|
2-July
|
63
|
4-Sept
|
5.2
|
Selection
|
3-July
|
62
|
4-Sept
|
5.3
|
Select
|
4-July
|
61
|
4-Sept
|
5.4
|
Select
|
5-July
|
60
|
4-Sept
|
5.5
|
Catching
|
6-July
|
59
|
4-Sept
|
6.0
|
Deploy
|
5-Sept
|
10
|
15-Sept
|
6.1
|
Global
|
16-Sept
|
9
|
15-Sept
|
6.2
|
Receive
|
17-Sept
|
8
|
15-Sept
|
Put the above table in a Gantt chart