Operations Management

Katie Posh runs an upscale nail salon. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parentheses):

Activity 1: Welcome a guest. (1 minute)
Activity 2: Clip and file nails. (3 minutes)
Activity 3: Paint. (5 minutes)
Activity 4: Dry. (10 minutes)
Activity 5: Check out the customer. (4 minutes)

Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following:

Need assignment help for this question?

If you need assistance with writing your essay, we are ready to help you!

OUR PROCESS

Order

Payment

Writing

Delivery

Why Choose Us: Cost-efficiency, Plagiarism free, Money Back Guarantee, On-time Delivery, Total Сonfidentiality, 24/7 Support, 100% originality

S1 does Activity 1.
S2 does Activities 2 and 3.
S3 does Activities 4 and 5.

The drying process does not require server 3’s constant attention; she/he needs to only escort the customer to the salon’s drying chair (equipped with fans for drying). The time to do this is negligible. There exists only one drying chair in the salon.

PN1. Which resource is the bottleneck of the process?

PN2. What is the utilization of server 2 (in decimal form)? Assume that there is unlimited demand and that the process only admits customers at the rate of the bottleneck.

PN3. What is the average labor utilization of the servers (in decimal form)? Assume that there is unlimited demand and that the process only admits customers at the rate of the bottleneck.

PN4. Assume a wage rate of $12 per hour. What are the direct labor costs for one customer (in dollars)?