1. During a project, Earned Value Analysis is performed and gives the following numbers: ;
; EV: 523,000; PV: 623,000; AC: 643,000.
; Which results are correct?
OUR PROCESS
Order
Payment
Writing
Delivery
Why Choose Us: Cost-efficiency, Plagiarism free, Money Back Guarantee, On-time Delivery, Total Сonfidentiality, 24/7 Support, 100% originality
;A. CV: +120,000; SV: +100,000
;B. CV: +100,000; SV: +120,000
;C. CV: -100,000; SV: -120,000
;D. CV: -120,000; SV: -100,000
Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution. ;