Problem 17-13
Here is a list of activity times for a project as well as crashing costs for its activities. Determine which activities should be crashed and the total cost of crashing if the goal is to shorten the project by three weeks as cheaply as possible. (Omit the “$” sign in your response.) |
Need assignment help for this question?
If you need assistance with writing your essay, we are ready to help you!
OUR PROCESS
Order
Payment
Writing
Delivery
Why Choose Us: Cost-efficiency, Plagiarism free, Money Back Guarantee, On-time Delivery, Total Сonfidentiality, 24/7 Support, 100% originality
Activity | Duration (weeks) | First Crash | Second Crash |
1-2 | 5 | $8 | $10 |
2-4 | 6 | 7 | 9 |
4-7 | 3 | 14 | 15 |
1-3 | 3 | 9 | 11 |
3-4 | 7 | 8 | 9 |
1-5 | 5 | 10 | 15 |
5-6 | 5 | 11 | 13 |
6-7 | 5 | 12 | 14 |
|
Activity | Cost | |||
First crash | $ | $ | $ [removed] | |